This page was translated by SYSTRAN      (comments, feedback ...)


A small good sets fire to in the medium of the underwater tunnel will recall us many memories... Ah, short-term profitability, what one would not make for it!!! Sieur Ponsolle was in a good place with the SNCF and in La Vie du Rail, it prefers the road solution, for a ex-railwayman, it is very intelligent...

You one will still need many innocent carbonized or gazed to put a little lead in the brain of these " brains "?

Eurotunnel proposes two solutions in drilled tunnel


Like held to recall it Patrick Ponsolle, president executive of Eurotunnel, Wednesday January 5 2000, it is in accordance with the obligations of the treaty of concession of 1986 (article 34.1) that Eurotunnel has just given to the French States and British a project of second fixed link under the Sleeve. Presented in December, this project aims to supplement the existing tunnel, «when the technical and economic conditions of realization of such a connection allow it and when the increase in the traffic justifies it without calling into question the awaited profitability of the first work ».
Without anything to prejudge possible realization, Eurotunnel thus entrusted to two consultants - French Scetauroute (Egis group) and the Maunsell British - the realization of a feasibility study of which we present the contents here. The treaty of concession evoked only one road link, but it was finally decided to also think of a railway link. The exercise comprised a relatively flexible schedule of conditions, the project especially having «to answer criteria of safety at least as rigorous as those of the existing tunnel », to be «complementary to current operating system », and «to offer a capacity adapted to the long-term forecasts of flow of the trans-manche traffic ».

Neither bridge, nor immersed work

If ten alternative projects of additional fixed link were the subject of a feasibility study, only two solutions in drilled tunnel were adopted.«The bridges and the immersed structures, as in 1996, presented insurmountable difficulties, while the recent technical developments as regards drilling make it possible to plan to dig tunnels of large diameter », indicates one at Eurotunnel. Scetauroute and Maunsell thus proposed a tunnel monotube 15 m in external diameter. A curious choice, when it is known that the experts of the underground works recognize as ideal the solutions bitube!
On the road assumption, the new Channel tunnel is equipped with two flagstones of bearing forming two levels reserved for the light vehicles, in a way identical to the work currently in construction in Paris area, on western A86. Here, each stage comprises two lanes and a hard shoulder.
As on western A86, the work accomodates neither heavy lorries nor coaches. And, in this case, the existing tunnel under the Sleeve is borrowed more only by the shuttles freight, Eurostar and the goods trains, the coaches continuing to be transferred onto shuttles with simple bridge.

On the railway assumption, the tunnel is equipped with a flagstone which receives two separate ways of railroad one-way for Eurostar and the goods trains.
In this case, the current tunnel is exclusively reserved for the Eurotunnel shuttles transporting the cars and the trucks.

Tunneller with ground pressure and voussoirs prefabricated

The fire resistance , of course, was taken into account in calculations.
Thus, the structure even of the tunnel largely takes part in it, by means of an exceptionally thick ring external (1 m) and flagstones of reinforced concrete floor. «As a need, an additional protection in the form of thermal plates would be added, specify the consultants. The whole of the road version was calculated on the basis of extreme assumption of fire during two hours, which corresponds to the fire of a tanker of 50 m3 hydrocarbons reaching 1350°C»a data to be taken with much precaution, the firemen being shown surprised by the violence of fire in the tunnel of Mont.Blanc, March 24, 1999.
In the project, it is expected that each stage has of its own distribution and its own sheath of extraction of the fume. In addition, a play of communication would make it possible to regulate the contribution of fresh air on each side of a fire starting from the nonaffected stage. Lastly, as it has been just decided for Mont Blanc, the tunnel would be equipped with two rescue stations, located at two thirds of the course and accomodating permanently of the personnel.
Same principles in the railway version which would be, it, equipped with an automatic stopping device of the trains, side pavements acting as device anti-derailment in addition.
Concerning underground work, the consultants estimate that they can be carried out using a tunneller with ground pressure. «This machine must make it possible to work either in closed mode, or in opened mode, and seems adapted to the excavation of the grounds met by the second fixed link », explain. The coating can be ensured by precasted concrete voussoirs. As for the works of accompaniment, they can, them, be embanked into traditional. Cast iron voussoirs would be used with the right of these works.


Which cost?
Except cost of land acquisitions, the road project is evaluated at 4,12 billion euros (27 billion francs), and the railway project to 4,57 billion euros (30 billion francs). These figures advanced by the consultants are regarded as «reasonable »by Eurotunnel, which estimates that the control of the costs will have to be guaranteed by a complete definition of the project before publication of the invitations to tender, and by an extreme rigour of these invitations to tender.

GUILLAUME DELACROIX Le Moniteur du BTP of 14-01-00